Very few fabrication customers refuse to pay. What they do is pay late, in instalments nobody agreed, after a reminder that came two weeks after the money was due. Meanwhile you have already bought the material, paid the fitters and started the next job on your own cash.
This is a structure problem and a habit problem, in that order.
The advance has one job: buy the material
An advance that does not cover the material you must purchase is not an advance. It is a loan you are making to the customer, secured on nothing.
Work out what the job requires in material and fittings before you set the advance. In most aluminium, UPVC and steel work that lands somewhere between forty and fifty percent of the job value. If the customer will not cover the material, that is important information about the customer, and it has arrived at the cheapest possible moment.
Tie stages to events, never to dates
"Thirty percent on 15 November" invites an argument, because the 15th arrives whether or not anything happened. "Thirty percent on delivery of material to site" does not, because both of you can see whether the material is at site.
A structure that works for most jobs:
- 50% on order confirmation — before anything is cut.
- 30% on delivery of fabricated material to site.
- 20% on completion of installation and handover.
The final slice should be small enough that losing it would not hurt badly, and large enough that the customer wants you to come back and finish snags. Twenty percent does both. Ten is too little to motivate you; forty is too much to leave outstanding.
Put the stages in the quotation, not in the conversation
Payment terms agreed verbally are payment terms that will be remembered differently. Three lines at the foot of the quotation, agreed when the customer is still choosing you rather than when they owe you money, is worth more than any amount of chasing later.
Include what is not included while you are there. Scaffolding, old frame disposal, electrical work, making good — the exclusions prevent the end-of-job deduction, which is how the final twenty percent most often goes missing.
Ask on the day, every time
This is the habit, and it is most of the battle.
A balance that falls due on Tuesday and is asked for on Tuesday gets paid. The same balance asked for the following Monday has already become, in the customer's mind, a thing that can wait — because you waited. The signal you send by following up promptly is not aggression. It is that your terms are real.
Twenty minutes every Monday, going down an overdue list oldest first, collects more money than any amount of tightening your terms.
What to say, concretely
Vague requests get vague responses. Compare:
- "Sir, please arrange the payment when possible."
- "The delivery stage of ₹14,412 fell due on 14 October against invoice INV/2026/0184. Could you release it today?"
The second is not ruder. It is specific, which makes it answerable, and it signals that you have a record rather than a grievance.
Keep the record in one place
You cannot follow up what you cannot see. The list you need is not total revenue — it is which customer owes how much and for how many days, oldest at the top. A notebook can do this. So can a spreadsheet. The important thing is that there is exactly one of them and you look at it weekly.
Three things worth refusing
- Starting work on a verbal confirmation with no advance. The number of jobs cancelled after material was cut is larger than anyone admits.
- Handing over before the completion payment on a customer who has already been late at an earlier stage. Past behaviour is the only predictor you have.
- Letting a snag hold the whole balance. Fix the snag quickly and ask again. A snag is a reason; after three weeks it becomes an excuse.